Project Summary

The City applied for an STP grant (Surface Transportation Program) in 2021 through the East-West Gateway Council of Governments.  The grant was approved, providing 80% reimbursement for all phases of the project: Design 2022, ROW 2023, Construction 2024. 

Project Update

Final Plans, Specifications, and Estimate were submitted to MoDOT in October, and were conditionally approved in late December. The project was advertised in early January, and bids are due 2/6. 