Street Resurfacing Project

Project Summary
The 2021 Street Resurfacing Project will include St. Clement Street, Ridgelawn Drive, and Westwind Drive. The existing asphalt surface will be removed first. If necessary, the underlying concrete will be repaired prior to an asphalt overlay. The asphalt and removal and replacement will each only take a day or two. However, we anticipate significant concrete repair will be needed, so the work will probably take several weeks.


Project Update and Schedule


Eleven bids were opened 2/23. A contract with Spencer Contracting was approved by the Board of Aldermen at their 3/8 meeting. Removal of the asphalt is scheduled to start April 15th, then concrete work would start the following week. Notification letters will soon be delivered to affected residents. 
Last Updated 4/9/21