Sidewalk Replacements

Project Summary
Typically the City replaces over 1000 linear feet of sidewalk each year under contract.  In 2018, we ramped-up to 3000 linear feet.  City crews replace additional sidewalks on an emergency basis.  The City marks the locations to be removed and replaced, then the contractor performs the work.  In most cases, the sidewalk is being replaced because adjacent tree roots have lifted the sidewalk, causing trip hazards.  In order to combat this issue, roots are trimmed, and when possible, a product called TripStop is installed.

Please note that neither the existing nor new concrete is "colored" concrete.  While there is some limestone-based concrete around the city, most of the concrete contains Meramec sand and gravel, which provides the orange/brown look.  While the new concrete initially appears to be a bright white, over time, the color mellows and the top layer of cement wears off, revealing the brown sand and gravel underneath.

Project Location and Schedule

The 2019 project will once again include about 3000 linear feet of sidewalk.  The subdivisions to be addressed have not yet been selected at this time.  The project will be bid out over the winter, with construction scheduled for late spring.

The Street Division can grind trip hazards or replace sidewalk slabs in extenuating circumstances.  Call Public Works at 835-6130 to report a trip hazard.

Updated 12/26/18