Topping Lane Drainage
Project Summary
The 2016 budget included the design of potential drainage improvements for Topping Lane.  Kuhlmann design Group (KdG) was hired to survey the street and provide design options.  

Project Update
Due to the cost of executing the project, the Board of Aldermen has split the project into phases. The 2017 budget includes funding storm sewer repairs.  Delaying the street work until 2018 will allow for more infill housing construction to be completed before adding curbs and resurfacing the street.
Updated 11/21/16