Topping Lane Drainage
Project Summary
The 2016 budget included the design of potential drainage improvements for Topping Lane.  Kuhlmann design Group (KdG) was hired to survey the street and provide design options.  
Due to the cost of executing the project, the Board of Aldermen  split the project into phases. The 2017 budget includes funding storm sewer repairs.  Delaying the street work until 2018 will allow for more infill housing construction to be completed before adding curbs and resurfacing the street.


Project Update

This summer, the box culvert running across the street from #10 to #7 will be modified, with additional inlets and piping installed in front of #7. A new inlet will also be installed between #20 and #22 Topping, along with some grading.  

Bids were opened March 20th, and Krupp Construction will be awarded the contract, pending Board approval at their March 27th meeting.  Construction will occur sometime over the summer.  A schedule will be posted once contracts are signed.

Updated 3/23/2017