Project Summary
Cracksealing is technically a maintenance activity rather than a capital improvement project.  However, since it occurs on the streets, and there may be questions, it is being included in this section.

Cracksealing is part of an overall pavement maintenance plan, preventing water and debris from getting into the joints and causing deterioration. While Des Peres has self-performed some cracksealing in the past, this will be our first widespread program. 

Project Location and Schedule
Nearly all of the concrete streets west of I-270 will be cracksealed this year, with other streets following in future years.

Bids for this project were opened on February 4th, and NuCoat Sealing was the lowest of eight bidders ($26,765.05).  The contract was approved by the Board of Aldermen February 22nd. The work took place in April and the first few days of May

Updated 5/6/16

Only the streets in green will be included in this year's project, due to budgetary limitations.