Concrete Street Replacement
Project Summary
Many of our older concrete streets consist of 5" of concrete on top of compacted soil. Due to the extensive failures of the existing pavement, the concrete street and underlying soil will be removed, and a new cross-section will be constructed, consisting of 4" of rock and 8" of concrete.  Slabs will be tied together using epoxy-coated steel rebars. Other than the cul-de-sacs, half the street will be removed and replaced at a time, to mitigate the effect of construction on homeowners.

Project Location and Schedule
Three streets are scheduled for complete concrete replacement this year: Belle Meade Road (east of Tricorn Lane), Briar Fork Court, and Lawnwood Drive. 

Bids were opened on March 16th, and the low bidder was Spencer Contracting. The contract was approved by Board of Aldermen at their March 28th meeting.

The preconstruction meeting occurred on 8/17, and work is expected to start 9/12.  Spencer Contracting will be sending this mailing to all affected residents.  The order of work will be: Lawnwood, Belle Meade, then Briar Fork Ct.

You may soon see colored paint and flags on the ground, which are the locations of underground utilities. 



Project Update
Spencer is scheduled to pour the west side of Lawnwood on Wednesday, 9/21.  Expect a complete closure of the street during the pour, due to concrete trucks.

While the concrete on Lawnwood cures for a week, work will take place on Belle Meade.

Updated 9/20/16