2017 Capital Improvement Projects

Street and Sidewalk Projects

Cracksealing
-completed

Sidewalk Replacement 
(Greenbriar Estates)-completed

Street Resurfacing 
(Claychester, Lilian, and Harwood)-in progress

Street Slab Replacement 
(Westledge Court)-completed

Ridgetree Lane: The cul-de-sac was replaced last year, but flaking occurred on some of the slabs over the winter.  Those slabs are scheduled for warranty replacement beginning Wednesday 9/20.  Please watch for signage on-site. 


Bridge-Design        

Oak Drive

Drainage    

Topping Lane-completed

Facilities

Salt Dome Roof Repairs-completed

Equipment

1 Ton Dump Truck with spreader and plow (replacement)-ordered

Backhoe and breaker (replacement)-received and in-use

Drop-hammer for skid-steer-received and in-use

Electronic Message Panel-received and in-use

I-270 Construction

MoDOT has two projects on I-270 starting this summer: Replacement of the Big Bend Bridge, and Resurfacing of I-270.  Please visit MoDOT's site for details.

Manchester Corridor Study (East of Ballas)
This study started in 2016 and was completed in 2017.  Presentations were given to the Board of Aldermen during a work session and to the Planning & Zoning Commission during a regular meeting.  Having this study in place puts the City in an excellent position to compete for federal project funding in the future, and provides a template to both MoDOT and developers.
Final Report
Presentations Slides