Park Construction Projects

Des Peres Park Phase 1


Tennis Courts, Pickleball Courts & Parking Lot


Improvements to Des Peres Park in 2019 include replacing the six asphalt tennis courts with six new post-tension concrete tennis courts, three pickleball courts, a parking lot, a unisex restroom, and trail connections. The city sent out construction bids in April 2019. 

Construction Schedule

 

5/28/2019 Construction Contracts presented to the Board of Alderman
6/10/2019 Cost reduction options submitted to Board of Alderman for review
7/1/2019 Notice to Proceed to Contractors
7/8/2019 Tennis Courts closed
7/26/2019 Demolition began
9/1/2019 Major grading work began
9/6/2019 Work halted due to City Hall/Des Peres Park water line
10/1/2019 New water service installed
10/4/2019 Water service for City Hall/Des Peres Park switched over from old service
10/7/2019 Grading resumes
10/17/2019 Complete Site Grading
10/16/2019 Begin Electrical Rough in
10/17/2019 Begin Comfort Station Construction
11/25/2019 Sport Lighting Poles Erected


(Tentative - pending weather delays)

12/16/2019 Anticipated Eastern Tennis Courts and Pickleball Courts Concrete Pour
12/16/2019 Northwestern Retaining Wall Construction
12/23/2019 Anticipated Western Tennis Courts and Shuffleboard Courts Concrete Pour


1/31/2020 Substantial Project Completion

After the concrete court surface has cured (minimum of 30 days), there must not be any rain in the forecast and the temperature has to be above 50 degrees to apply the painted court surfacing.

Project Overview


Des Peres Park Tennis Court Project Presentation

2019-07-31 Court Demolition
18-1207 DP Construction Sign
2019-03-02 Des Peres Park Tennis Court Project Preliminary Construction Documents